JG Engineering were working on behalf of D Morgan PLC a major infrastructure and developments civil engineering contractor. The Air Phase 2 development is a large-scale development of an old MOD airfield that has been split in half. One site residential and the other side commercial with a large spine road through the middle of the site. JG Engineering were involved in all surveys and setting out aspects of the works. Initially the site was cut and filled to the required levels. Over 100,000m3 of Class 1A imported fill was brought into site by road wagon to achieve the required finished levels. A residential spine road was then constructed through the residential spine of the works. A series of swales and culverts were also constructed. As part of the works a large pump station was constructed that was 10.5m in diameter and 18 meters deep.